Tiburon seeks savings as ponds park estimate reaches $3.7 million

Tiburon parks commissioners asked designers Sept. 15 to trim the cost of a planned park at the former sanitation ponds near McKegney Green, now projected at $3.7 million.

RHAA VIA TOWN OF TIBURONA rendering presented to Tiburon’s Parks, Open Space & Trails Commission on Sept. 15 shows the proposed park at the former sanitation-ponds site near McKegney Green. Commissioners, looking to bring down the $3.7 million cost, asked designer RHAA Landscape Architecture & Planning to scale back the lawn, find savings in a $360,000 awning and consider a single beach volleyball court in place of the two shown.
Francisco Martinez
By FRANCISCO MARTINEZ · 2 min read

Tiburon parks officials are looking for ways to bring down the cost of a park at the former sanitation-ponds site near McKegney Green, where the projected construction price has climbed to $3.7 million.

The Parks, Open Space & Trails Commission asked designers Sept. 15 to reduce the cost of a lawn, price an option for one beach volleyball court instead of two and find savings in a $360,000 shade structure, among other changes to the 60%-complete design. A 60% set fixes a project’s layout and materials and is detailed enough to price, but it is not the final construction drawings.

The meeting followed an informal, hourlong feedback session at which consultants from Mill Valley-based park designers RHAA Landscape Architecture & Planning fielded questions about the park’s design as it stood.

Commissioners also asked the designers to determine whether the proposed adjustable basketball hoops would be strong enough to withstand players hanging on them; to paint the proposed ball wall so it blends into its surroundings; to consider removing some seats closer to McKegney Green; to replace the extended stone seating along the site’s banks with groups of stone seats; and to consider driftwood instead of bike gates on the pedestrian-only curve that connects the Old Rail Trail to the multiuse path in front of the Richardson Bay Sanitary District.

Read the complete story in our e-edition, or SUBSCRIBE NOW for home delivery and access to the digital replica.

Comment on this article on Nextdoor.

A version of this story appeared in the Sept. 23, 2026, print edition of The Ark. See something wrong? Request a correction.
Add The Ark to Google Preferred Sources
Recent Stories
Belvedere parks panel makes Cliff Lane path to the shore its 2027 focus Tiburon crews box in downtown drains to keep tidewater off streets Belvedere painter Gordon Studer among 8 peninsula artists at ICB’s Big Open A former Wall Street banker finds her pace in Tiburon Tiburon dances in the light at fifth annual Diwali celebration
In print every Wednesday
Front page of The Ark, Wednesday, November 11 Nov. 11, 2026 E-EDITION
The Ark in your inbox

Local news from Tiburon, Belvedere and Strawberry, delivered by email.

Support The Ark’s commitment to high-impact community journalism.

The Ark, named the nation's best small community weekly for 2026, is dedicated to delivering investigative, accountability journalism with a mission to increase civic engagement and participation by providing the knowledge that can help sculpt the community and change lives. Your support makes this possible.

SUBSCRIBE Make a contribution